DOI: 10.5176/2301-394X_ACE15.173

Authors: Sunan Suksai

Abstract:

This research is a study of factors affecting the delay of the construction period by working together during construction between main contractors and nominated sub-contractors in high rise building at Bangkok and vicinity. The focus of the factors which cause delays to the structural work, architectural work, electrical work and mechanical work and sanitary work in the General Contract (Domestic-Sub-contract) and Nominated Sub-contract . This study used questionnaires and interviews as a tool for collecting data. Data analysis methods to compare the average frequency in order to know the factors that make each type of construction delays and statistical methods Independent-Sample t-test to find out
the critical factors to the construction both of the contrast delay.
The results showed that factors which cause delays affecting the construction period consisted of not working together as team-work, project management experience is not enough and be deficient in skill of communicate and coordinate. It also found that the delay factor of five critical factors that make construction in terms of structure, architecture, electrical – mechanical and sanitation was always delayed. Factors include delays resulting from not working together as team work, period of the plan laid down, delayed delivery area, delays in the approval and construction items and shortage of skilled labor, or labor shortages during the season so aware of the critical factors that delay the construction above. And find ways to prevent construction delays caused by these factors.

Keywords: delay, main contractor, nominated subcontractor, high rise building

simplr_role_lock:

Price: $0.00

Loading Updating cart...
LoadingUpdating...